Timeline for the development and delivery of the Port Access Road

  • 2020 – Construction complete
  • January 2019 – Main construction commenced
  • Summer 2018 – Funding decision
  • Spring 2018 – Advance translocation of species
  • Spring 2018 – Submission of business case to the Department of Transport (DfT)
  • February 2018 – Advance vegetation clearance completed
  • Autumn 2017 – Detailed Design completed, construction works tendered
  • April 2017 – Newhaven Enterprise Zone established
  • Summer 2016 – Lewes District Council Joint Core Strategy adopted by Lewes District Council and South Downs National Park
  • Spring 2016 – East Sussex County Council Local Transport Plan Implementation Plan published
  • Late 2015 – Construction of Phase 1 completed by developer
  • Autumn 2014 – Local Growth Fund monies provisionally awarded to the scheme through Coast 2 Capital Local Enterprise Partnership (LEP’s) Strategic Economic Plan
  • 2012 to 2013 – Scheme details reviewed and funding allocated from East Sussex County Council Capital programme
  • 2007 – Planning permission renewed and construction started but was not completed
  • 2002 – Planning permission renewed
  • 1996 – Original planning permission given for the Newhaven Port Access Road